Staff Answer
Jul 04, 2026 - 01:27 AM
Two people average about 1,000 sq ft per hour per coat. Dynamic Race Works completed their entire 20,000 sq ft race shop in one weekend with their own in-house crew. For floors over 10,000 sq ft, plan one person mixing plus 3–4 rolling, and each coat finishes in about 5–6 hours.